The print layout for the C1GanttView project is determined by the following elements:
-
Header/Footer - Divides the GanttView into three parts. Each part represents a column. You can add content and format it for each part.
-
GanttChart- Includes the GridView and ChartView; it represents all task information and graphics representation.
-
Legend - Represents various patterns of bar styles that have been used in the project as well as an annotation area to look up in the ChartView.
The following GanttChart illustrates the printing elements used for the print layout:

See Also